Schedule Til Demolition Day (24 May - 2 Jun)

It has taken (what felt like many) months between completion in early March til this past Monday when Lane Engineers gave their final approval for the renovations.
This is the schedule for up to Demolition date:
24 May, Fri    - Abestos testing at apartment [Action: Sergio to attend]
27 May, Fri    - Abestos report from H.A. Consultants
30 May, Mon - Memorial Day, yay! and sigh...
31 May, Tue   - DOB filing by Agouti Consulting
1 Jun, Wed     - Electrical filing at DOB [Action: Greg the electrician]
2 Jun, Wed     - Plumbing filing at DOB (approval may take days/weeks) [Action: Plumber]
2 Jun, Wed     - *Victor starts Demolition [Action: Kane to email Brenda for no-plumbing-filing permission]